. A machining center in a job shop for a local fabrication company has five unprocessed jobs remaining at a particular point in time. The jobs are labeled 1, 2, 3, 4,and 5 in the order that they entered the shop. The respective processing times and due dates are given in the table below. Job number 1 2 3 4 5 Processing Time 11 29 31 1 2 Due Date 61 45 31 33 32 a. Determine the sequence of jobs, the average flow time, average tardiness and average number of jobs at the work center for each of the following rules:
Q: Lazer Technologies Inc. (LTI) has produced a total of 20 high-power laser systems that could be used…
A: Answer) (a) Estimating the learning rate by calculating the average learning rate with each doubling…
Q: At the campus copy shop, six jobs have arrived in the order shown (A, B, C, D, E, and F) at the…
A: Job Due in (hours) Duration (hours required)A81.65B5.51.2C4.50.85D61.3E41.85F71.55
Q: Examine how skills levels of operators and requested service levels as factors impacting warehouse…
A: Inventory management refers to the process of overseeing, controlling, and organizing a company's…
Q: Consider the bill of materials (BOM) shown below. If inventory consists of 3 units of B, 2 of F, and…
A: In BOM: Net Requirement = (Gross requirements) - (On-hand inventory)
Q: Develop a EOQ solution and calculate total relevant costs for the gross requirements in the…
A: MRP stands for Material Requirements Planning. It is a computer-based inventory management system…
Q: J.C. Howard's medical testing company in Kansas wishes to assign a set of jobs to a set of machines.…
A: The production process involves all those activities which are important for meeting the demand of…
Q: Suppose orders are placed only at review time. Find the optimal period and the optimal order…
A: Annual demand (D) = 1200Ordering cost (S) = 50Purchase cost (P) = 30Carrying cost (H) = 10% of 30 =…
Q: What does sustainability mean to an importer of wood based in the UK
A: Sustainable sourcing, manufacture, and use of wood products in a way that reduces negative…
Q: Which can be considered going overboard on your marketing resume? Select an answer: infographics.…
A: A marketing resume in simple terms is defined as a document that showcases the educational…
Q: Bracket Manufacturing uses a Kanban system for a component. Daily demand is 1,100 units. Each…
A: To determine the number of Kanban card sets authorized, we can use the following formula:Number of…
Q: Calculate the Critical Ratios (CR): (Enter all responses rounded to two decimal places.) Job 1 2 3 4…
A: Scheduling is the process of organizing as well as planning the activities that are important for…
Q: What were the benefits of batch processing versus time sharing before it became the norm?
A: Before time sharing became the norm, batch processing was the main method of computing. Batch…
Q: Solve the following dilemma using the logic from the level and stage of moral reasoning from…
A: Morality development is the process through which an individual develops their understanding of…
Q: The management of two different sized sachets of maize meal—5 kg and 3 kg—is entrusted to you. The…
A: Best value for money refers to getting the most benefit or quality for the price paid by the…
Q: 3. Bolufsen Resort has 40,000 rooms available each year. Operational figures for the years between…
A: Operational data is the information that is generated as well as collected during the daily…
Q: What can be done to make the many routine chores of the NPT easier to handle?
A: The Nuclear Non-Proliferation Treaty (NPT) is an international treaty aimed at preventing the spread…
Q: As business operations become more complex and competitive, and as data volumes grow, companies are…
A: Companies are looking for methods to use simulation and machine learning to acquire insights and…
Q: In an unbalanced transportation problem where total supply exceeds total demand, the supply…
A: Generally speaking, there will frequently be ">=" (more than or equal to) inequality in the…
Q: What are the key considerations and strategic trade-offs for businesses when developing a policy on…
A: Corporate Social Responsibility (CSR) refers to a business approach that incorporates ethical and…
Q: A company makes three types of candy and packages them in three assortments Assortment I contains 4…
A: Linear programming is a mathematical optimization technique used to find the best possible solution…
Q: Why construct? Mapping a project in the absence of architecture. Product influence.
A: Project management is the practice of planning, organizing, and executing tasks and resources to…
Q: 4 eBook Hint Print References Problem 8-2 (Static) The owner of Genuine Subs, Inc., hopes to expand…
A: To solve this problem, we'll need to use the fixed costs per month, variable cost per unit, selling…
Q: In what ways would Imana Foods benefit from applying the lean principles of pull processing, waste…
A: The Lean principles, also known as the Toyota Production System (TPS) principles, are a set of…
Q: 2.4 A quality engineer in charge of a coffee filter pack production line was concerned about the…
A: Control charts are graphical tools that are used by the company to monitor a process over time and…
Q: What is the break-even quantity? Round your answer to the nearest whole number. boxes If sales…
A: Selling Price per box = SP = $19.86Fixed Costs = FC = $60000Variable Cost per box = VC = $10.19
Q: Current flight delays are affecting schedules and passengers around the world. A quick Google search…
A: ***Below answer is explained taking into consideration the Operations management point of…
Q: Find the Optimal Economic order quantity for the following: Annual Demand - 3600 units Ordering…
A: Annual demand (D) = 3600 unitsOrdering Cost (S) = $50Storage cost = 20% of unit price
Q: Imagine a small or medium-sized business's culture. Are societal or cultural barriers preventing…
A: Business culture is the values, belief custom, attitude, behavior, and practice that is followed in…
Q: In a decentralized system, there are many modules that may be used again. To what extent is it true?
A: For a decentralized system to be flexible, reusable, and effective, modularization is a crucial…
Q: It is essential to comprehend the differences between project management and software project…
A: Project management ia s process with different stages like initiating, planning, executing, closing,…
Q: What is a project charter? why is it so important per PMI to have a project charter?
A: Project management is the discipline of planning, organizing, and executing projects to achieve…
Q: Peter is considering operating a local business in the textile, clothing and footwear sector. Peter…
A: FabricWear is a sustainable textile, apparel, and footwear firm with big plans for the future.…
Q: Carefully analyse the figure below and answer the question that will follow: Scope definition…
A: The numerous actions and components that contribute to the forward and reverse flow of commodities…
Q: Using decision tree analysis, determine whether the company should conduct the test market.
A: A decision tree is a graphical representation of decision-making under uncertainty. It is a tool…
Q: What are some of the advantages of utilizing dynamic programming?
A: Dynamic programming is very helpful in problem-solving and optimization. Here are some…
Q: Having a solid understanding of the project's map will be beneficial. taking into account the…
A: In the realm of product development, having a comprehensive understanding of the project's roadmap…
Q: Learning the project's road plan is essential. taking product impact into account.
A: Learning the project's road plan and considering the product impact are crucial factors in…
Q: Describe the steps involved in assessing country risk once all relevant information has been…
A: Once all relevant information has been gathered for assessing country risk, the following steps can…
Q: Do you understand how dynamic programming is used?
A: The following is the basic conceptual understanding of dynamic programming:By segmenting more…
Q: Problem 7-11 (Algo) How many observations should a time study analyst plan for in an operation that…
A: Standard deviation (S) = 2.6 minutes / pieceError (e) = 1.1 minutesConfidence level of=95.5%
Q: (2) A company sells its products for $50 per unit. It has annual fixed cost of $300,000 and variable…
A: Selling Price per unit = SP = $50Annual Fixed Cost = FC = $300,000Variable Costs per unit = VC =…
Q: Santa Cruz Bottling is a manufacturer of organic soft drinks on the coast of central California. Its…
A: Santa Cruz Bottling wants to set up a new plant and searching for a best location. The following…
Q: Component freedom means that one part should be able to be swapped out for another part that is made…
A: The idea of component freedom has become more significant when we try to evolve in a rapidly…
Q: Increasing payment terms from customers Increasing inventory safety stock Decreasing payment terms…
A: The time it takes for a business to convert its investments in inventory and other resources into…
Q: A firm requires 90,000 units (D) over a 120-day production period and is placing 2-orders of equal…
A: Total cost is the summation of holding cost i.e. the cost that is incurred by the company at the…
Q: Do you consider that it is necessary to partition a large project into lesser tasks? Is this type of…
A: Project management is the practice of planning, organizing, and overseeing the execution of a…
Q: Mark Price, the new productions manager for Speakers and Company, needs to find out which variable…
A: Regression Analysis is a statistical method where individuals and corporations can study the…
Q: A company begins a review of ordering polices for its continuous review system by checking the…
A: *In the given image, some figures are somehow unclear, but still i tried to mention the correct…
Q: Referencing the scenario provided in Assessment 1, and following the guidance provided by the…
A: Sustainable competitive advantage refers to the unique set of qualities, resources, or capabilities…
Q: As the manager overseeing Audiot and Co., you commenced the planning of audit work for a new client,…
A: The audit is conducted by professionals who have deep knowledge regarding the operations of the…
Trending now
This is a popular solution!
Step by step
Solved in 3 steps with 9 images
- A machine center in a job shop for a local fabrication company has five unprocessed jobs remaining at a particular point in time. The jobs are labeled A, B, C, D, and E in the order that they entered the shop. The respective processing times and due dates are given in the table below. What is the sequence the of jobs by CR rules? Job Processing Time Due Date A 10 32 B. 55 34 C. 11 31 60 35Currently a company that designs Web sites has five customers in its backlog. The time since the order arrived, processing time, and promised due dates are given in the following table. The customers are ready to be scheduled today, which is the start of day 190. Customer Time Since Order Arrived (days ago) Processing Time (days) Due Date (days from now) Upper AA 6 18 66 Upper BB 3 24 58 Upper CC 2 32 100 Upper DD 10 22 26 Upper EE 8 12 50 a. Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of average flow time and average days past due. Part 2 Using the FCFS (first come, first served) decision rule for sequencing the customers, the order is: Sequence 1 2 3 4 5 Customer D E A B C Part 3 Using…b. The Healthy Food Restaurant, a 24-hour restaurant, faces changing requirements from hour tohour. More workers are needed for peak hours, and fewer are needed in between. The followingTable 6 (below) shows the worker requirement for the first 12 hours in the restaurant:Table 6. Staff Requirement at the Healthy Food RestaurantTime Period 10AM11AM12PM1PM2PM3PM4PM5PM6PM7PM8PM9PMRequirement 8 10 12 12 9 7 6 7 9 10 12 8AssignedOn DutyOverstaffed8(i) You are required to apply the first-hour principle to staff each hour with the required number ofcafeteria staff, showing how many staff are on duty each given hour, the number of staffyou have assigned to work each hour and any overstaffing for each hour. i. Schedule the staff to work in 8-hour shifts.
- The Hickory Company manufactures wooden desks. Manage-ment schedules overtime every weekend to reduce the backlogon the most popular models. The automatic routing machineis used to cut certain types of edges on the desktops. The fol-lowing orders need to be scheduled for the routing machine: The due dates reflect the need for the order to be at its nextoperation.a. Develop separate schedules by using the FCFS and EDDrules. Compare the schedules on the basis of average flowtime and average past due hours.b. Comment on the performance of the two rules relative tothese measuresCurrently a company that designs Web sites has six customers in its backlog. The time since the order arrived, processing time, and promised due dates are given in the following table. Job Time Since Order Arrived (days ago) Processing Time (days) Due Date (days from now) A 6 18 48 B 4 22 52 C 1 30 70 D 10 14 28 E 7 12 56 F 5 20 62 Develop a schedule by using the first-come, first-served (FCFS) rule and calculate the average flow time and average days past due for the schedule. Develop a schedule by using the earliest due date (EDD) rule and calculate the average flow time and average days past due for the schedule. Comment on the performance of the FCFS and EDD rules relative to average flow time and average days past due.Currently a company that designs Web sites has five customers in its backlog. The day when the order arrived, processing time, and promised due dates are given in the following table. The customers are listed in the order of when they arrived. They are ready to be scheduled today, which is the start of day 190. Customer Time SinceOrder Arrived(days ago) ProcessingTime (days) Due Date(days fromnow) A B C D E 10 8 6 3 2 20 12 28 24 32 26 50 66 58 100 a. Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of average flow time and average days past due.b. Comment on the performance of the two rules relative to these measures. Which one gives the best schedule? Why?
- On Monday morning, Baxter Industries has the following jobs waiting for processing in two departments, milling, and drilling, in that order. Time Required (hours) Job Mill Drill 216 7 11 327 6 10 462 8 4 519 5 8 258 3 5 617 12 15 Develop a minimum makespan schedule using Johnson's rule. The schedule using Johnson's rule is - - - - - . Choose the correct Gantt chart with the minimum makespan schedule. The correct graph is .WorkPro is a small manufacturer. It uses a job process for production. The following sample of jobs are listed in the order that they were received. Job Due Date Operation Time P 5 1 Q 20 8 R 8 5 S 11 6 T 3 12 When the shortest operating time (SOT) rule is applied to the sample of jobs, the resulting sequence is: A. Choos the following answer choice. T, P, R, S, Q R, S, T, P, Q P, Q, R, S, T P, R, S, Q, T B. In the WorkPro example above, average flow time for the sample of jobs when sequenced by the shortest operating time (SOT) rule is approximately: 19.8 14.2 4.8 6.4 C. In the WorkPro example above, average lateness for the sample of jobs when sequenced by the earliest due date (EDD) rule is approximately: Group of answer choices 10.4 4.8 7.8 5.8 D. Using the sample of jobs in the WorkPro example above, the shortest operating time (SOT) rule appears more attractive than the earliest due date (EDD) rule…At the University Hospital, five blood samples must bescheduled through a blood-testing laboratory. Eachsample goes through up to four different testing stations.The times for each test and the due dates for eachsample are as follows:Sample Test Station/Hours Due Date (hours)1 A/1, B/2, C/3, D/1 62 B/2, C/3, A/1, D/4 103 C/2, A/3, D/1, C/2 84 A/2, D/2, C/3, B/1 145 D/2, C/1, A/2, B/4 12a. Using a Gantt chart, schedule these five samples in priority order of earliest due date first.b. Assume that the capacity of each test station (A, B, C and D) is doubled. Prepare an FCS for this situation.c. What are the bottleneck work centers in part a of the problem. Suggest capacity additions that might be needed.
- Q5(a) Wonderloaf Bakery has orders for five specialty jobs A, B, C, D, and E that must be processed sequentially through two work centers baking and decoration. The amount of time in hours required for the jobs is shown in Table Q5(a). Determine the schedule sequence that minimizes the total elapsed time for five jobs using the following techniques; (i) Critical ratio; (ii) Johnson's Rule; Table Q5(a) Job (Orders Received) Processing time(hrs) Baking Hours remaining Decoration A 13 3 в 18 4 17 8 2 D 15 7 4 E 22 6 10A nursing home must schedule nurses in a manner that balances providing adequate patient care while keeping costs down. From historical records, administrators can project the minimum number of nurses to have on hand during each day/time slot. This data is shown below. Shift Time Slot Minimum number of nurses needed 1 12 am-4 10 2 4 am-8 6 3 8 am-12 8 4 12 pm-4 12 5 4 pm-8 10 6 8 pm-12 14 Nurses must start work at the beginning of one of the four-hour shifts (starting as early as 12 am midnight or as late as 8pm evening) and work for eight hours. Nurses who begin working at 8 pm will work until 4 am the next morning. Formulate and solve the nurse-scheduling problem so as to minimize excess stagging while satisfying minimum staffing requrements. What is the value of total excess staffing?A manufacturer is designing a product layout for a new product productionIt plans to use a production line for 8 hours per day in order to meet forecasted demand of 70 units per day. The product requires 7 tasks in total. These tasks are namelyABC, D, E, F, and Grespectively. Task A does not have any predecessor to startTo start Task B.it requires Task A to be completedStarting tasks needs, the task B to be completed. Also, starting task Dneeded task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed task Fto be completed. The processing times for tasks, ABC, D. E. and G are 2.8, 2.1, 0.9, 1.0, 1.2, 1.8 and 4.7 minutes respectively. What should be the cycle time in minutes? a 4.7 b. None is the correct answer Oc 7.5 d6.86 e.