Question 1 Problem Statement:  Stakeholder and Project Quality Management   “Hercules Creative Solutions” has successfully bagged two research and development related projects from ministry of science and technology. You are working on one of a project as senior project manager which is related to develop a gadget for the help of physically disabled persons in their day to day commuting. The main challenge for you and your team is that neither you nor any of your team members have ever done this type of project. USAID and one of a leading bank are the sponsors of this project. The designing of the product has been outsourced to one of a very famous engineering firms of the country. For the procurement purpose, two potential vendors are on board. The company you are working for is a multinational company and has very strict procurement procedure and procurement audit is mandatory at the end of the project. Stringent quality standards have to be followed which includes but not limited to rigorous testing of all the features, user friendliness and ability to recover in case of software/ hardware errors. After completing the pilot, the product was released for beta test to selected users that were arranged by the sponsors. Multiple users complained that this product is difficult to use and at times does not work as expected. In other words, end users were not satisfied with the design and working of this product. Hercules Creative Solutions has decided to recall all the pieces from the end users and planned to perform a hardware/ software upgrade. The main stakeholders are not happy with this situation as have complained earlier multiple times during the course of this project for not being involved. The external auditors have also pointed out some serious compliance issues related to procurement process. After getting know about the situation of this project, answer the following questions. Required:   1.Identify all the internal and external stakeholders of this project. In which category, the cost of recalling the product will fall? List down some of the risks while working on this project. In your opinion, what were the reasons of this project’s failure? What could have been done by Hercules Creative Solutions to avoid or minimize the situation faced due to product failure?   Question 2                                                                                         Problem Statement:  Project Control and Monitoring   You are working on a manufacturing project having a budget of PKR 3,600,000 and expected time of its completion is one year. There is an ideal condition that your budget and work are evenly spread across the duration of the project that is twelve month. At the end of forth month, the senior management has called a meeting and invited all the stakeholders to brief about the status of the project. You being the PM of this project is giving the presentation to all the attendees and informed that project is on schedule and PKR 1,800,000 have already been spent on the project.   Required: Calculate Cost and Schedule Variance What is SPI and CPI of the project? Estimate at completion and Estimated time to complete?  Question 4 Problem Statement:  Procurement Management   Aisha wants to join Pakistan’s biggest construction firm as a project manager. She is giving a case study to read it thoroughly so that a discussion could be made on this as part of interview. The project was about to construct a road between two mega cities. It was a mega project involving a lot of contracts with different vendors. The project manager had made a number of cost plus fixed fee (CPFF) type of contracts with multiple vendors. For example, a contract was made with a vendor to lease a machine. The cost of leasing the equipment is 1200 $ per day while the cost of an outright purchase is 96000 $ and a daily maintenance cost of 200 $.The duration of completing the activity for which this equipment was leased is 150 days. No evidence of contract closing were found in the documentation of project. The firm and their sponsors bear a loss at the completion of this project. Required:    Identify all the mistakes made by the project manager by providing proper justification.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
icon
Concept explainers
Topic Video
Question

Question 1

Problem Statement:  Stakeholder and Project Quality Management

 

“Hercules Creative Solutions” has successfully bagged two research and development related projects from ministry of science and technology. You are working on one of a project as senior project manager which is related to develop a gadget for the help of physically disabled persons in their day to day commuting. The main challenge for you and your team is that neither you nor any of your team members have ever done this type of project. USAID and one of a leading bank are the sponsors of this project. The designing of the product has been outsourced to one of a very famous engineering firms of the country. For the procurement purpose, two potential vendors are on board.

The company you are working for is a multinational company and has very strict procurement procedure and procurement audit is mandatory at the end of the project. Stringent quality standards have to be followed which includes but not limited to rigorous testing of all the features, user friendliness and ability to recover in case of software/ hardware errors.

After completing the pilot, the product was released for beta test to selected users that were arranged by the sponsors. Multiple users complained that this product is difficult to use and at times does not work as expected. In other words, end users were not satisfied with the design and working of this product. Hercules Creative Solutions has decided to recall all the pieces from the end users and planned to perform a hardware/ software upgrade. The main stakeholders are not happy with this situation as have complained earlier multiple times during the course of this project for not being involved. The external auditors have also pointed out some serious compliance issues related to procurement process.

After getting know about the situation of this project, answer the following questions.

Required:

 

1.Identify all the internal and external stakeholders of this project.

  1. In which category, the cost of recalling the product will fall?
  2. List down some of the risks while working on this project.
  3. In your opinion, what were the reasons of this project’s failure?
  4. What could have been done by Hercules Creative Solutions to avoid or minimize the situation faced due to product failure?

 

Question 2                                                                                        

Problem Statement:  Project Control and Monitoring

 

You are working on a manufacturing project having a budget of PKR 3,600,000 and expected time of its completion is one year. There is an ideal condition that your budget and work are evenly spread across the duration of the project that is twelve month. At the end of forth month, the senior management has called a meeting and invited all the stakeholders to brief about the status of the project. You being the PM of this project is giving the presentation to all the attendees and informed that project is on schedule and PKR 1,800,000 have already been spent on the project.

 

Required:

  1. Calculate Cost and Schedule Variance
  2. What is SPI and CPI of the project?
  3. Estimate at completion and Estimated time to complete? 

Question 4

Problem Statement:  Procurement Management

 

Aisha wants to join Pakistan’s biggest construction firm as a project manager. She is giving a case study to read it thoroughly so that a discussion could be made on this as part of interview. The project was about to construct a road between two mega cities. It was a mega project involving a lot of contracts with different vendors. The project manager had made a number of cost plus fixed fee (CPFF) type of contracts with multiple vendors. For example, a contract was made with a vendor to lease a machine. The cost of leasing the equipment is 1200 $ per day while the cost of an outright purchase is 96000 $ and a daily maintenance cost of 200 $.The duration of completing the activity for which this equipment was leased is 150 days. No evidence of contract closing were found in the documentation of project. The firm and their sponsors bear a loss at the completion of this project.

Required:

 

 Identify all the mistakes made by the project manager by providing proper justification.

 

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.