Rocky Mountain Tire Center sells 14,000 go-cart tires per year. The ordering cost for each order is $35, and the holding cost is 30% of the purchase price of the tires per year. The purchase price is $21 per tire if fewer than 200 tires are ordered, $16 per tire if 200 or more-but fewer than 5,000-tires are ordered, and $14 per tire if 5,000 or more tires are ordered. a) How many tires should Rocky Mountain order each time it places an order? Rocky Mountain's optimal order quantity is 5000 units (enter your response as a whole number). b) What is the total cost of this policy? Total annual cost of ordering optimal order size = $ (round your response to the nearest whole number).

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

part b i need help with please

Rocky Mountain Tire Center sells 14,000 go-cart tires per year. The ordering cost for each order is $35, and the holding cost is 30% of the purchase price of the tires per year. The purchase
price is $21 per tire if fewer than 200 tires are ordered, $16 per tire if 200 or more-but fewer than 5,000-tires are ordered, and $14 per tire if 5,000 or more tires are ordered.
a) How many tires should Rocky Mountain order each time it places an order?
Rocky Mountain's optimal order quantity is 5000 units (enter your response as a whole number).
b) What is the total cost of this policy?
Total annual cost of ordering optimal order size = $
(round your response to the nearest whole number).
Transcribed Image Text:Rocky Mountain Tire Center sells 14,000 go-cart tires per year. The ordering cost for each order is $35, and the holding cost is 30% of the purchase price of the tires per year. The purchase price is $21 per tire if fewer than 200 tires are ordered, $16 per tire if 200 or more-but fewer than 5,000-tires are ordered, and $14 per tire if 5,000 or more tires are ordered. a) How many tires should Rocky Mountain order each time it places an order? Rocky Mountain's optimal order quantity is 5000 units (enter your response as a whole number). b) What is the total cost of this policy? Total annual cost of ordering optimal order size = $ (round your response to the nearest whole number).
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 13 images

Blurred answer
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.