Southwestern University (SWU), a large state college in Stephenville, Texas, 30 miles southwest of the Dallas/Fort Worth metroplex, enrolls close to 20,000 students. In a typical town-gown relationship, the school is a dominant force in the small city, with more students during fall and spring than permanent residents. A longtime football powerhouse, SWU is a member of the Big Eleven conference and is usually in the top 20 in college football rankings. To bolster its chances of reaching the elusive and long-desired number-one ranking, in 2000, SWU hired the legendary Phil Flamm as its head coach. One of Flamm's demands on joining SWU had been a new stadium. With attendance increasing, SWU administrators began to face the issue head-on. After 6 months of study, much political arm wrestling, and some serious financial analysis, Dr. Joel Wisner, president of Southwestern University, had reached a decision to expand the capacity at its on-campus stadium. Adding thousands of seats, including dozens of luxury skyboxes, would not please everyone. The influential Flamm had argued the need for a first-class stadium, one with built-in dormitory rooms for his players and a palatial office appropriate for the coach of a future NCAA champion team. But the decision was made, and everyone, including the coach, would learn to live with it. The job now was to get construction going immediately after the 2015 season ended. This would allow exactly 270 days until the 2016 season opening game. The contractor, Hill Construction (Bob Hill being an alumnus, of course), signed his contract. Bob Hill looked at the tasks his engineers had outlined and looked President Wisner in the eye. "1 guarantee the team will be able to take the field on schedule next year," he said with a sense of confidence. "I sure hope so," replied Wisner. "The contract penalty of $10,000 per day for running late is nothing compared to what Coach Flamm will do to you if our opening game with Penn State is delayed or canceled." Hill, sweating slightly, did not need to respond. In football-crazy Texas, Hill Construction would be mud if the 270-day target was missed. Back in his office, Hill again reviewed the data (see Table 3.6) and noted that optimistic time estimates can be used as crash times. He then gathered his foremen. "Folks, if we're not 75% sure we'll finish this stadium in less than 270 days, I want this project crashed! Give me the cost figures for a target date of 250 days-also for 240 days. I want to be early, not just on time!" TABLE 3.6 ACTIVITY DESCRIPTION B C D Southwestern University Project K L Bonding, insurance, tax structuring Foundation, concrete footings for boxes Upgrading skybox stadium seating Upgrading walkways, stairwell, elevators Interior wiring, lathes Inspection approvals E F G H Painting 1 Hardware/AC/metal workings 1 Tile/carpet/windows Final detail work/cleanup TIME ESTIMATES (DAYS) PREDECESSOR(S) OPTIMISTIC MOST LIKELY PESSIMISTIC CRASH COST/DAY 20 20 A A С B E D. F G H H J LK 30 25 0.1 25 10 20 0.1 20 30 65 60 50 30 0.1 30 20 25 10 0.1 25 80 100 100 *3*28238 0.1 $1,500 3,500 4,000 1,900 9,500 0 2.500 2,000 2,000 6,000 0 4,500 REQUIRED: 1. Develop a network (AON) drawing for Hill Construction and determine the critical path. How long is the project expected to take? 2. What is the probability of finishing in 270 days? 3. If it is necessary to crash to 250 or 240 days, how would Hill do so, and at what costs? As noted in the case, assume that optimistic time estimates can be used as crash times.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
MANAGEMENT SCIENCE
TOPIC: Project Management | Due on November 29, 2023 (2:30pm, Yellow Paper)
Southwestern University (SWU), a large state college in Stephenville, Texas, 30 miles southwest of the
Dallas/Fort Worth metroplex, enrolls close to 20,000 students. In a typical town-gown relationship, the school is
a dominant force in the small city, with more students during fall and spring than permanent residents.
A longtime football powerhouse, SWU is a member of the Big Eleven conference and is usually in the
top 20 in college football rankings. To bolster its chances of reaching the elusive and long-desired number-one
ranking, in 2009, SWU hired the legendary Phil Flamm as its head coach.
One of Flamm's demands on joining SWU had been a new stadium. With attendance increasing, SWU
administrators began to face the issue head-on. After 6 months of study, much political arm wrestling, and some
serious financial analysis, Dr. Joel Wisner, president of Southwestern University, had reached a decision to
expand the capacity at its on-campus stadium.
Adding thousands of seats, including dozens of luxury skyboxes, would not please everyone. The
influential Flamm had argued the need for a first-class stadium, one with built-in dormitory rooms for his players
and a palatial office appropriate for the coach of a future NCAA champion team. But the decision was made, and
everyone, including the coach, would learn to live with it.
The job now was to get construction going immediately after the 2015 season ended. This would allow
exactly 270 days until the 2016 season opening game. The contractor, Hill Construction (Bob Hill being an
alumnus, of course), signed his contract. Bob Hill looked at the tasks his engineers had outlined and looked
President Wisner in the eye. "Iguarantee the team will be able to take the field on schedule next year," he said
with a sense of confidence. "I sure hope so," replied Wisner. "The contract penalty of $10,000 per day for running
late is nothing compared to what Coach Flamm will do to you if our opening game with Penn State is delayed or
canceled." Hill, sweating slightly, did not need to respond. In football-crazy Texas, Hill Construction would be
mud if the 270-day target was missed.
Back in his office, Hill again reviewed the data (see Table 3.6) and noted that optimistic time estimates
can be used as crash times. He then gathered his foremen. "Folks, if we're not 75% sure we'll finish this stadium
in less than 270 days, I want this project crashed! Give me the cost figures for a target date of 250 days-also
for 240 days. I want to be early, not just on time!"
TABLE 3.6
ACTIVITY
A
B
C
D
E
F
G
H
I
Southwestern University Project
DESCRIPTION
Bonding, insurance, tax structuring
Foundation, concrete footings for boxes
Upgrading skybox stadium seating
Upgrading walkways, stairwells, elevators
Interior wiring, lathes
Inspection approvals
Plumbing
Painting
Hardware/AC/metal workings
J Tile/carpet/windows
K Inspection
L
Final detail work/cleanup
PREDECESSOR(S) OPTIMISTIC
20
20
A
A
C
B
E
D. F
H
H
J
LK
30
25
0.1
25
10
20
8
0.1
20
TIME ESTIMATES (DAYS)
MOST LIKELY PESSIMISTIC CRASH COST/DAY
30
40
80
50
30
0.1
30
20
25
10
0.1
25
100
100
35
0.1
35
12
0.1
$1,500
3,500
4,000
1,900
9,500
0
2,500
2,000
2,000
6,000
0
4,500
REQUIRED:
1. Develop a network (AON) drawing for Hill Construction and determine the critical path. How long is the
project expected to take?
2. What is the probability of finishing in 270 days?
3. If it is necessary to crash to 250 or 240 days, how would Hill do so, and at what costs? As noted in the
case, assume that optimistic time estimates can be used as crash times.
Transcribed Image Text:MANAGEMENT SCIENCE TOPIC: Project Management | Due on November 29, 2023 (2:30pm, Yellow Paper) Southwestern University (SWU), a large state college in Stephenville, Texas, 30 miles southwest of the Dallas/Fort Worth metroplex, enrolls close to 20,000 students. In a typical town-gown relationship, the school is a dominant force in the small city, with more students during fall and spring than permanent residents. A longtime football powerhouse, SWU is a member of the Big Eleven conference and is usually in the top 20 in college football rankings. To bolster its chances of reaching the elusive and long-desired number-one ranking, in 2009, SWU hired the legendary Phil Flamm as its head coach. One of Flamm's demands on joining SWU had been a new stadium. With attendance increasing, SWU administrators began to face the issue head-on. After 6 months of study, much political arm wrestling, and some serious financial analysis, Dr. Joel Wisner, president of Southwestern University, had reached a decision to expand the capacity at its on-campus stadium. Adding thousands of seats, including dozens of luxury skyboxes, would not please everyone. The influential Flamm had argued the need for a first-class stadium, one with built-in dormitory rooms for his players and a palatial office appropriate for the coach of a future NCAA champion team. But the decision was made, and everyone, including the coach, would learn to live with it. The job now was to get construction going immediately after the 2015 season ended. This would allow exactly 270 days until the 2016 season opening game. The contractor, Hill Construction (Bob Hill being an alumnus, of course), signed his contract. Bob Hill looked at the tasks his engineers had outlined and looked President Wisner in the eye. "Iguarantee the team will be able to take the field on schedule next year," he said with a sense of confidence. "I sure hope so," replied Wisner. "The contract penalty of $10,000 per day for running late is nothing compared to what Coach Flamm will do to you if our opening game with Penn State is delayed or canceled." Hill, sweating slightly, did not need to respond. In football-crazy Texas, Hill Construction would be mud if the 270-day target was missed. Back in his office, Hill again reviewed the data (see Table 3.6) and noted that optimistic time estimates can be used as crash times. He then gathered his foremen. "Folks, if we're not 75% sure we'll finish this stadium in less than 270 days, I want this project crashed! Give me the cost figures for a target date of 250 days-also for 240 days. I want to be early, not just on time!" TABLE 3.6 ACTIVITY A B C D E F G H I Southwestern University Project DESCRIPTION Bonding, insurance, tax structuring Foundation, concrete footings for boxes Upgrading skybox stadium seating Upgrading walkways, stairwells, elevators Interior wiring, lathes Inspection approvals Plumbing Painting Hardware/AC/metal workings J Tile/carpet/windows K Inspection L Final detail work/cleanup PREDECESSOR(S) OPTIMISTIC 20 20 A A C B E D. F H H J LK 30 25 0.1 25 10 20 8 0.1 20 TIME ESTIMATES (DAYS) MOST LIKELY PESSIMISTIC CRASH COST/DAY 30 40 80 50 30 0.1 30 20 25 10 0.1 25 100 100 35 0.1 35 12 0.1 $1,500 3,500 4,000 1,900 9,500 0 2,500 2,000 2,000 6,000 0 4,500 REQUIRED: 1. Develop a network (AON) drawing for Hill Construction and determine the critical path. How long is the project expected to take? 2. What is the probability of finishing in 270 days? 3. If it is necessary to crash to 250 or 240 days, how would Hill do so, and at what costs? As noted in the case, assume that optimistic time estimates can be used as crash times.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 8 steps with 7 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.