[The following information applies to the questions displayed below.] In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed In 2026. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of completion. Balance Sheet (Partial) Current assets: Current liabilities: 3. Complete the Information required below to prepare a partial balance sheet for 2024 and 2025 showing any items related to the contract Note: Do not round Intermediate calculations. 2024 2024 2025 $ 2,523,000 $ 3,177,000 6,177,000 1,800,000 2,070,000 3,630,000 1,835,000 3,400,000 0 2025 2026 $ 1,980,000 0 0 4,300,000 4,765,000

CONCEPTS IN FED.TAX.,2020-W/ACCESS
20th Edition
ISBN:9780357110362
Author:Murphy
Publisher:Murphy
Chapter3: Income Sources
Section: Chapter Questions
Problem 88P
icon
Related questions
Question
Required Information
[The following information applies to the questions displayed below.]
In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for
$10,000,000. The road was completed In 2026. Information related to the contract is as follows:
Cost incurred during the year
Estimated costs to complete as of year-end
Billings during the year
Cash collections during the year
Westgate recognizes revenue over time according to percentage of completion.
Balance Sheet (Partial)
Current assets:
Current liabilities:
2024
3. Complete the Information required below to prepare a partial balance sheet for 2024 and 2025 showing any Items related to the
contract
Note: Do not round Intermediate calculations.
0
2024
$ 2,523,000
6,177,000
2,070,000
1,835,000
0
2025
$ 3,177,000
1,800,000
3,630,000
3,400,000
2025
0
2026
$ 1,980,000
0
0
4,300,000
4,765,000
Transcribed Image Text:Required Information [The following information applies to the questions displayed below.] In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed In 2026. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of completion. Balance Sheet (Partial) Current assets: Current liabilities: 2024 3. Complete the Information required below to prepare a partial balance sheet for 2024 and 2025 showing any Items related to the contract Note: Do not round Intermediate calculations. 0 2024 $ 2,523,000 6,177,000 2,070,000 1,835,000 0 2025 $ 3,177,000 1,800,000 3,630,000 3,400,000 2025 0 2026 $ 1,980,000 0 0 4,300,000 4,765,000
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
CONCEPTS IN FED.TAX., 2020-W/ACCESS
CONCEPTS IN FED.TAX., 2020-W/ACCESS
Accounting
ISBN:
9780357110362
Author:
Murphy
Publisher:
CENGAGE L