Void Ratio (e) Cost Php/m3 400.00 Borrow Pit A 0.82 В 1.1 250.00 C 0.9 450.00 0.78 600.00
Void Ratio (e) Cost Php/m3 400.00 Borrow Pit A 0.82 В 1.1 250.00 C 0.9 450.00 0.78 600.00
Engineering Fundamentals: An Introduction to Engineering (MindTap Course List)
5th Edition
ISBN:9781305084766
Author:Saeed Moaveni
Publisher:Saeed Moaveni
Chapter20: Engineering Economics
Section: Chapter Questions
Problem 36P
Related questions
Question
A proposed embankment fill requires 8000 ?3 of compacted soil. The void ratio of
the compacted fill is specified as 0.70. Four borrow pits are available as described in the table
which list the respective void ratios of the soil and cost per cubic meter for moving the soil to the
proposed construction site. Make necessary calculations to select pit from which the soils should
be bought to minimize the cost. Assume specific gravity to be the same at all pits.
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps with 2 images
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you
Engineering Fundamentals: An Introduction to Engi…
Civil Engineering
ISBN:
9781305084766
Author:
Saeed Moaveni
Publisher:
Cengage Learning
Engineering Fundamentals: An Introduction to Engi…
Civil Engineering
ISBN:
9781305084766
Author:
Saeed Moaveni
Publisher:
Cengage Learning