Construction Accounting And Financial Management (4th Edition)
Construction Accounting And Financial Management (4th Edition)
4th Edition
ISBN: 9780135232873
Author: Steven J. Peterson MBA PE
Publisher: PEARSON
Question
Book Icon
Chapter 4, Problem 9P
To determine

Ascertain the estimated cost at completion of project and variance for each cost.

Blurred answer
Students have asked these similar questions
A company is constructing a new production facility. The following costs have been incurred:  Site preparation costs $50,000 Architects’ fees $26,000 Legal fees $10,000 Purchase of site $200,000 Costs incurred to relocate employees to the new facility $30,000 Administration costs $50,000 Total costs $366,000 The architects’ fees relate to the design of the new facility and the legal fees relate to legal advice received on the contract to purchase the site. The total value that should be recognized as Property, Plant and Equipment for the new facility should be   Question 10Answer a. $ 314,000 b. $ 324,000 c. $ 344,000 d. $ 286,000
8. A contractor has a contract to construct the sanitary sewer, water line, storm drain, and street lighting for a new subdivision. The contractor uses the cost codes in Figure 2-6. The original estimate for the sewer was $25,000, and a $3,200 change order has been approved to add a manhole. The sewer work has been completed by the contractor at a cost of $27,365. The original estimate for the waterline was $31,000, and no changes have been made to the budget. The costs to date for the waterline are $31,300 and it is estimated that it will take another $450 to complete the waterline. The water line is being installed by the contractor. The original estimate for the storm drain was $17,000, and no changes have been made to the budget. The contractor has paid $7,236 for materials and estimates that it will cost $9,764 to install the storm drain. The contractor will install the storm drain. The original estimate for the outside lighting was $23,600, and no changes have been made to the…
In connection with surfacing a new highway, a contractor has a choice of two sites on which to set up the asphalt- mixing plant equipment. The contractor estimates that it will cost $1.25 per cubic yard mile (yd³ -mile) to haul the asphalt-paving material from the mixing plant to the job location. Factors relating to the two mixing sites are as follows: Cost Factor Average hauling distance Monthly rental of site Cost to set to and remove equipment Hauling expense Flagperson Site A 6 miles $1,200 $17,000 $1.25 / yd³ -mile Not required Site B 4.3 miles $5,500 $25,000 $1.25 / yd³ -mile $96 / day The job requires 50,000 cubic yards of mixed-asphalt-paving material. It is estimated that four months (17 weeks of five working days per week) will be required for the job. Compare the two sites in terms of their total costs. Assume that the cost of the return trip is negligible. A) Which is the better site? B) For the selected site, how many cubic yards of paving material does the contractor…
Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
FINANCIAL ACCOUNTING
Accounting
ISBN:9781259964947
Author:Libby
Publisher:MCG
Text book image
Accounting
Accounting
ISBN:9781337272094
Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:Cengage Learning,
Text book image
Accounting Information Systems
Accounting
ISBN:9781337619202
Author:Hall, James A.
Publisher:Cengage Learning,
Text book image
Horngren's Cost Accounting: A Managerial Emphasis...
Accounting
ISBN:9780134475585
Author:Srikant M. Datar, Madhav V. Rajan
Publisher:PEARSON
Text book image
Intermediate Accounting
Accounting
ISBN:9781259722660
Author:J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:McGraw-Hill Education
Text book image
Financial and Managerial Accounting
Accounting
ISBN:9781259726705
Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:McGraw-Hill Education